Contaminated Land Working Group
Remediation and the Waste Management Regulatory Regime
AGS Position Paper (Updated December 2002)
(PDF Version)
1. Legal Background
1.1
The EA document "Guidance on the Application of Waste Management Licensing
to Remediation" (Version 2.0, January 2001) classifies contaminated soil
arisings as "controlled waste". This is based on its designation as
"directive Waste" [ie it is waste as defined by the EC Waste Framework
Directive]. This requires a three stage test;
- it is within the scope of the Waste Framework Directive
- it is listed in Part II of Schedule 4 of the 1994 Waste
Management Licensing Regulations
- it must have been discarded or intended to have been
discarded.
1.2
The EA Guidance (2001) states that the contaminants themselves can be considered
waste as they have been '"abandoned or control of them has been lost"'
and since "the soil is not discrete from the contaminants, that too will be
waste".
1.3
In addition uncontaminated natural arisings from service and foundation
excavations on development sites may be classified as waste. The EA have
indicated that the purpose of such excavations is to install elements of a
development and not to 'win' material. They would, therefore, conclude that the
intention is to discard the surplus arisings and consequently they would be
classified as waste.
1.4
As a consequence of these positions virtually all development sites in England
and Wales will be handling and re-using waste materials. For these operations to
comply with the law the activities will either have to be exempt from Waste
Management licensing or operate under a Waste Management Site Licence. An
alternative promoted by the EA is to operate a mobile plant license but the
circumstances in which these can be used are largely restricted to specialist
forms of ground remediation.
2. EA Interpretation
2.1
The EA position on exemptions from waste management licensing is set out in
their Guidance (2001). The implications of the guidance are that even if there
is an appropriate use for the 'waste', if it requires any form of treatment or
containment the operation will not be an exempt activity.
2.2
In its simplest from, if there is made ground on a site which requires some form
of cover to render the site suitable for its intended use, that material cannot
be moved or reused below the proposed cover layer without a Waste Management
Site Licence. This situation applies on many redevelopments of brownfield sites.
In order to ensure that the cover layer is not contaminated during the
development process and the required thickness is achieved, its application is
usually left to the last activity on site. Technically, under the current EA
position, regrading of the site to achieve the required landform prior to
placing the cover layer should be subject to a site licence.
2.3
In the past AGS members have also reported that EA officers are applying the requirements of
waste management licensing to routine geotechnical treatment of clean natural
soils with poor physical properties (for example lime/cement stabilisation of
soft clays, installation of sand drains to accelerate settlement of compressible
soils etc.) However in 2002 the EA stated in writing that geotechnical
treatment of natural uncontaminated soils would not be considered a licensable
activity.
3. Implications for Remediation
3.1
There are major implications for all developments and a significant disincentive
for brownfield developments as a result of this guidance and its current
interpretation by the EA.
3.2
The requirements for exemptions for reusing any suitable made ground will merely
generate paperwork both for the developers and the EA in registering the
exemptions but otherwise should not cause major problems. It should be noted
however that on the basis of the current EA position, most developments would
require to register exemptions.
3.3
The major issue however, is that of the requirement for a Waste Management Site
Licence for reusing made ground which is not suitable without 'containment or
treatment' together with the subsequent surrender of the licence. The EA
Guidance (2001) suggests that only "significant or substantial
amounts" of regrading would require a licence and suggests that the
relevant enforcement positions would be used to define this amount. The EA
Functional Enforcement Guidelines include for 1,000m3 of in-situ treatment,
which in the context of site regrading would be a very small amount. The
alternatives under the current position are:
- To apply for a waste management licence to allow reuse of
these materials on-site or
- To take all made ground off site to an appropriately
licensed landfill. (Clearly for many sites this is likely to be uneconomic
and is certainly not a sustainable solution).
3.4
The delays and red tape required for the application and monitoring of a Waste
Management Licence alone will create a major disincentive for many development
projects. In addition there will be issues of perception associated with the
presence of a Waste Management Licence and the potential affect on the value and
onward sale of the development. Institutional investors are likely to be very
reluctant to invest in a development, which will be subject to a waste
management licence.
3.5
Although all types of developments are affected, the most sensitive issue will
be in selling houses on sites that are subject to a current Waste Management
Licence. With the majority of developments, remediation and site regrading
activities will continue throughout the development process (e.g. when a
development occurs in phases and the early phases are being occupied or sold as
development occurs elsewhere on the site). Thus, even without allowing for
delays in applying for surrender, an active waste management licence is likely
to be in place for all the potential occupations and sales on such sites.
3.6
The option of a mobile plant license is promoted by the EA. The advantage is
that the license is applied to the ‘plant’ and therefore leaves the site
when the licensed operation is complete. The
issue of potential blight associated with a Waste Management License discussed
in paragraph 3.5 is therefore avoided. However it should be noted that this approach has been
developed by the EA largely to cover specialist ground improvement techniques
and cannot be applied to most standard site regrading operations. The advantage
is that the license is applied to the 'plant' and therefore leaves the site when
the licensed operation is complete.
4. AGS Conclusions and Recommendations
In the first version of this paper, the following conclusions
were reached and recommendations made. Added in italics are comments on
developments since version 1 of this paper was produced.
4.1
AGS members have numerous clients operating in the development market. It is our
collective opinion that the presence of a Waste Management Site License will
have a major impact on the viability of all brownfield developments and
virtually render houses on such sites unsaleable. Even if the house buying
public are unaware of the issues, conveyancing lawyers have indicated that they
would advise both mortgage companies and house buyers not to invest in
properties whilst an active licence is in place.
4.2
It is our conclusion that these difficulties arise from the application of the
waste management regulatory regime to inappropriate circumstances (ie
development sites are not landfills or sites of waste management). Neither the
existing planning nor waste management regimes provide appropriate or adequate
administrative control on redevelopment sites where remediation of land
contamination is taking place as a part of that redevelopment.
4.3
AGS therefore strongly advise that the guidance on waste management licensing on
redevelopment sites is reviewed. If this does not occur there is likely to be a
major impact on the government target set in PPG 3 for the reuse of brownfield
sites. It is recommended that this review should critically examine:
- The EA interpretation of its definition of
"waste" on development sites. It is accepted that the legal
definition of waste derives from the EU directive which in itself is not
open to challenge. Nevertheless, AGS considers there remains room for the
EA to review its interpretation of the directive definition in the context
of contaminated soils.
- Extending the exemptions in Schedule 3 of the Waste
Management Licensing Regulations to include the reuse of marginally
contaminated soil on redevelopment sites. AGS understands that the EA
have made recommendation to DEFRA for additional exemptions to schedule 3
but that these do not address the specific issue of routine regrading
activities on constructions sites. AGS considers there remains an option to
extend the range of exemptions.
- Clarify the position regarding the use of geotechnical
processes to treat natural soils. Although the EA have produced a
produced a letter indicating that these operations due not fall under the
control of the waste management licensing regime, to avoid confusion, AGS
recommends that this advice is formally issued in Guidance.
4.4
For the long term it is recommended that Government should develop a new
statutory implement for bespoke licensing of site remediation, which would
remove this activity from the Waste Management Licensing regime.
In 1999 Government made commitments to prepare a new
regime to regulate contaminated land remediation projects. No progress was made
until in December 2001 when industry representative including AGS met with
officials to launch an initiative which would involve this Working Party in
drafting new legislation - a "Single Regeneration Permit". The
original intention of this Permit was for it to be used for ex site/ in situ
soil treatment schemes, replacing the separate mobile plant licenses, site
working plans and discharge consents. The AGS has a concern that the Remediation
Permit (RP) as currently drafted would not provide a solution to certain issues
relating to construction activities such as excavation, movement and replacement
of soils and has suggested a series of exemptions. A government group has been
set up to develop the proposal but the likely date for further consultation is
unknown.
|